Design work

Outpatient clinic of Primary health care in rural areas (1 - 2 doctors without housing)

General data:

Project name:
Outpatient clinic of Primary health care in rural areas (1-2 doctors without housing)

Consequence (responsibility) class of the building: CC1

Degree of fire resistance: 2

Building area: 251,00 m2

Floors: 1

Floor height: 3.5 m.

Construction volume: 1320 m3

Total building area: 218.30 m2

Capacity: visits per shift: 30 people

Number of employees: 8 people

Heat consumption, total: 8750 W

Specific heat output of the heating system: 40 W / m

Water consumption: 1.52 m³ / day

Sewerage: 0.85 m³ / day

Power consumption: 45.9 kW.

Annual electricity consumption: 114.75 thousand kW.year.

Duration of construction, including the preparatory period: 4.5 months.

Labor intensity of construction: 1864 people days

Constructions and materials

Foundations: Precast-monolithic reinforced concrete

Wall panels: Three-layer reinforced concrete insulated structures. Insulation - expanded polystyrene with fire retardant PSB-S 25, 150 mm thick along the p. 7075

Columns: Prefabricated reinforced concrete, section 400x400mm, series 1.020.1-2с / 89

Crossbars: Prefabricated reinforced concrete, section height 6700mm for series 1.020.1-2s / 89

Building covering slabs: Ribbed prestressed insulated, according to p.7075. Insulation with fire retardant expanded polystyrene PSB-S 25, thickness 215mm.

Hip roof: Wooden rafters and posts

Partitions: Knauf plasterboard systems on a metal frame

Floor: ceramic tiles, linoleum, concrete

Doors: Metal

Windows: Metal-plastic

Exterior decoration

Plinth: Plinth siding

Exterior Walls: Vinyl Siding